The appointment of NGOs for the above components is under progress, the status as of March 20, 2007 is as follows:
| Preparation of Draft Operating Guideline and Presentation of the Same |
Complete |
| Comments on Draft Operating Guideline |
Complete |
| Finalization Operating Guidelines |
Complete |
| "Clean Yamuna Manch Programme" |
| Shortlisting of NGOs |
Complete |
| Finalization of RFP Documents |
Complete |
| JBIC Concurrence of RFP document |
Complete |
| Issue of RFP document |
Complete |
| Receipt of Technical & Financial Proposals |
Complete |
| Evaluation & Recommendation of Technical Proposal |
Complete |
| JBIC concurrence |
Complete |
| Financial Negotiations with the first ranked NGO |
Failed |
| Process to call second ranked NGO |
Complete |
| Financial Negotiations with the second ranked NGO |
in progress |
| Signing of Contract with NGOs |
in progress |
| "Other PP&A Programme" ( Socio Economic & Environmental upgrdation programme, School Health & Hygiene programme and Innovative Programme) |
| Preparation of EOI & RFP Document for Selection of NGOs |
Complete |
| Finalization of EOI Document for Selection of NGOs |
Complete |
| Publication of EOI |
Complete |
| Evaluation & recommendation for shortlisting |
Complete |
| JBIC concurrence |
Complete |
| Orientation and Sensitization to PIAs, ULBs, NGOs |
Complete |
| Issue of RFP-Document ( Except Socio Economic & Environmental upgrdation of CTC neighborhood programme) |
Complete |
| Receipt of Technical and Financial Proposals (Last two progress) |
Complete |
| Evaluation of Technical Proposal (Documentation Part)by PMC |
Complete |
| Presentation by NGOs to the selection Committee for Evaluation |
in progress |