PMU Consultants for Physical Implementation of Five Components in Delhi
The appointment of consultants for this component is under progress, the status as of March 20, 2007 is as follows:
Preparation of EOI & RFP Documents |
Complete |
Publication of EOI |
Complete |
Evaluation and Recommendation for Shortlisitng |
Complete |
Comments on RFP Documents |
Complete |
Finalization of RFP Documents |
Complete |
Issue of RFP Documents |
Complete |
Receipt of Technical & Financial Proposal |
Complete |
Evaluation and Recommendation of Technical Proposal |
Complete |
Financial Negotiation with the Consultant |
Complete |
Signing of Contract with Consultant |
Complete |
|
 |