The appointment of Consultants for this Component is under progress, the Status as of March 31, 2008 is as follows:
| Package: STP at Okhla |
| Approval of DPR by NRCD |
Complete |
| Commencement of Work by Contrctors |
Complete |
| Package: STP at Keshopur |
| Review of DPR |
Complete |
| Approval of DPR by NRCD |
in-progress |
| Recommendation of Work Advisory committee for award of work |
Complete |
| Approval by Board (DJB) |
Awaited |
| Package: Bela Road Trunk Sewer |
| Review of DPR |
Complete |
| Recasting of DPR |
in-progress |
| Evaluation & Recommendation of Technical Bids |
in-progress |
| Approval by Board (DJB) |
Awaited |
| Package: Wazirabad Road Trunk Sewer |
| Review of DPR |
Complete |
| Recasting of DPR |
in-progress |
| Commencement of Work by Contrctors |
Complete |
| Package: Ring Road Trunk Sewer |
| Approval of DPR by NRCD |
Complete |
| Slice A : Commencement of Work by Contractors |
Complete |
| Slice B : Commencement of Work by Contractors |
Complete |
| Prepration of DPRs for YAP-III (Wastewater management schemes for Nazafgarh, Sahadra & Supplementry drains in Delhi) |
| Evaluation & Recommendation of Technical Bids |
in-progress |