The appointment of contractors for the above components is under progress, the status as of March 20, 2007 is as follows:
| Review of DPR (Combined - Land Acquisition & Remaining Works) |
Complete |
| Preparation of Revised DPR for Land Acquisition |
Complete |
| Review of Revised DPR for Land Acquisition |
Complete |
| Preparation of Land Acquisition documents |
Complete |
| Sanction of revised DPR for Land Acquisition and release of Fund |
Complete |
| Review of DPR (Works) |
Complete |
| Survey & Soil Investigation |
Complete |
| Preparation of Revised DPR (Works) |
Complete |
| Comments on Revised DPR (Works) |
Complete |
| Finalisation of DPR |
Complete |
| Sanctioning of Revised DPR (Works) |
Complete |
| Preparation of Draft PQ Document for appointment of Contractor |
Complete |
| Finalization of PQ document |
Complete |
| Notification of PQ document for four Package |
Complete |
| Notification of PQ document for three Package |
Complete |
| PQ for four Package |
Complete |
| Issue of Tender Document for four packages |
Complete |